Details
-
Change
-
Resolution: Unresolved
-
Medium
-
None
-
None
-
S2O Sprint 34
-
GxP
-
A
Description
As a PC1 Planner, I want the system to delete planned orders in firm horizon when approving any NOR or OCR linked to the ES2O scenario.
Desc: System should recalculate the firm horizon when submitting the NOR/OCR based on the below formula:
Firm Horizon = Max (90 , Last Order Date)
qTest: Test Execution
Attachments
Issue Links
- has to be done after
-
OS-20210 Requirement Gathering : OS-20202 - NOR/OCR for eS2O scenarios
- Closed
-
OS-20211 Analysis : OS-20202 - NOR/OCR for eS2O scenarios
- Closed
- relates to
-
OS-20378 Test Script review : OS-20202 - NOR/OCR for eS2O scenarios
- Done
-
OS-20379 Testing : OS-20202 - NOR/OCR for eS2O scenarios
- Done
-
OS-20380 Development & Unit testing : OS-20202 - NOR/OCR for eS2O scenarios
- Done
-
OS-20381 Test Case Preperation : OS-20202 - NOR/OCR for eS2O scenarios
- Done
-
OS-20382 Peer Code review : OS-20202 - NOR/OCR for eS2O scenarios
- Done
- links to
-
TC-3980 001_Verify user is able to delete planned orders in firm horizon when approving NOR Action
-
TC-3981 002_Verify user is able to delete planned orders in firm horizon when approving OCR Action
-
TC-3982 003_Verify user should not be able to delete planned orders in firm horizon when deleting NOR Action
-
TC-3983 004_Verify user should not be able to delete planned orders in firm horizon when deleting OCR Action