Uploaded image for project: 'OSCAR'
  1. OSCAR
  2. OS-15253

S2O Test Script Automation

Insert Lucidchart DiagramSend email
    XporterXMLWordPrintable

Details

    • Task
    • Resolution: Completed
    • Medium
    • 9.0
    • None
    • S2O
    • None

    Description

      AMP Planner-Scenario (STD )-NOR-Approve and Reject -  Completed

      PC1 Planner-Scenario (STD )-NOR-Approve and Reject -  Completed

      AMP Planner-Scenario (STD )-OCR-Approve and Reject - Completed

      PC1 Planner-Scenario (STD )-OCR-Approve and Reject - Completed

       

      Happy flow E2E flow of Cutover :  Upload cutover details and validate the details after submit and db table. Validation in weekly PIR inventory and History page -Completed 

       

       

      Attachments

        Activity

          People

            SWETHD U Raja, Divya Swetha
            KHANS167 Khan, Sufiya
            Votes:
            0 Vote for this issue
            Watchers:
            1 Start watching this issue

            Dates

              Created:
              Updated:
              Resolved:

              Time Tracking

                Estimated:
                Original Estimate - 3 days Original Estimate - 3 days
                3d
                Remaining:
                Remaining Estimate - 0 minutes
                0m
                Logged:
                Time Spent - 1 week, 1 day
                1w 1d